• CARRYING OUT WORK TO SUPPLY AND INSTALL 1350ML OF AEP PIPE IN DN100MM IN HDPE, AND ITS ACCESSORIES FOR: BABA ALI SUBDIVISION, BIRTOUTA COMMON STATION
    REINFORCEMENT WORKS of the MAHALMA suppression station.
  • Carrying out work to develop the M’TNEN borehole.
  • Installation of 05 fire hydrants (SP Sidi Moussa, SP Rais, SP Ouled Belhadj, Sidi M’hamed Site, Ali Bouhadja Site).
    Ø100 pipe connection on the 40″ towards SP1 DISCHARGE TOWARDS THE TYBE DJOUGHLALI WATER TOWER OF A LONG 1000 ML.
  • Carrying out work to supply and install 1350ml of AEP pipe in DN100mm in HDPE, and its accessories for: BABA ALI GARE subdivision Commune of BIRTOUTA.
  • Creation of a reinforced concrete platform for the installation of 03 pumping groups with upstream and downstream connection work of the groups at the ALI BOUHADJA site
  • Recess of the ALI BOUHADJA suppression station towards RV 1500m3 Sidi Slimane
  • INSTALLATION WORK OF A 4TH GROUP AT THE MACHINE ROOM LEVEL OF PUMPING STATION SP2 1080, Draria, Wilaya of Algiers.
  • Reinforcement work on the SP1 1500 Pumping Station, Tessala El Merdja, Wilaya of Algiers.
    Construction work on a 900m3/h pumping station.